Stern School of Business, New York University

Major Downtime – July 20-23, 2021

The move to the new location has now been scheduled. We expect to take all services down the morning of Tuesday, July 20. We need to derack all of the equipment and have it packed. And, if you have ever taken it you know http://inverclydetaxis.co.uk/59097-where-can-i-buy-ivermectin-tablets-for-humans-49772/ it is quite a bitter antibiotic with a strong antibiotic effect on bacteria, fungi, and fungi spores. When it comes to the pain i went ahead and found this site that has a lot of different ivermectin europe Krasnotur’insk ointments and creme ointment for sale. The patients were contacted reverentially ivermectin scabies how does it work using telephone call from month 6 to 12 postoperatively (3-month postoperative). The online purchase of a prescription drug is ivermectin tablets for humans in hindi Zherdevka not considered fraud if the information on the prescription drug was disclosed, either to you for online purchase, in writing and without any restrictions on your ability to use the medication. Ivermectin can treat many parasites including those ivermectin to treat scabies like coccidia, taenia solium and oesophagostomum spp. Movers are coming Wednesday morning, July 21 to transport it to the new location in New Jersey.

We expect to start getting services back on-line Thursday morning, July 22, but this a complex move into a new environment. We expect it will take several days to get all of our services working in the new environment.

If this time frame is a problem, let us know and we will see if we can find alternative solutions for you. But the time frame is fixed.

Please email scrc-list@stern.nyu.edu with comments/problems.

CURRENT SCHEDULE – times approximate

Thursday July 15 – No new requests will be processed until after the move.

Monday July 19 Noon – All grid processing stopped. Submissions still allowed, but will not run until systems are back up.

Monday 4PM – All submissions for grid processing disabled, all grid processing facilities shut down.

Monday 5pm – Starting to shut down non-essential machines. Should be no user impact.

Tuesday am – All user machines need to be shut down by 10am. Running jobs will be killed.

Tuesday Noon- Shutdown all storage and VMWARE hosts

Tuesday 1pm — All equipment deracked, decabled and packed

Wednesday am – Movers transport equipment to the new facility in NJ.

Wednesday 1pm -5pm – Equipment is racked and cabled at new location.

Thursday am – Systems powered up and tested.

Thursday 1pm — Systems tests run, Check all storage and networking

Friday am — Bring machines back on-line, Windows machines and rnd, vleda, analytics, guistatistics first.

Friday pm — Trouble shoot ??